October - November 2013

October - November 2013

11/15/2013

Aksubaevsky Branch

On site “Construction of the auto road “Chistopol-Aksubayevo-Nurlat” – Chuvashskoye Yenoruskino” – Ilyashkino in Aksubayevsky district of the Republic of Tatarstan” the works are finished.

11/14/2013

Suburban Branch

On site “Reconstruction of the auto road “M-7 “Volga” – “Pervoye Maya” – Kamysh in Pestrechinsky district of the Republic of Tatarstan” road signs are being mounted.

11/07/2013

Аrsky Branch

Metal road safety barriers 978 meters long, road signs and warning posts were mounted on site “Construction of the auto road Nizhnyaya Korsa – Verkhnyaya Korsa in Arsky district of the Republic of Tatarstan”.

11/07/2013

Mamadyshsky Branch

Construction of the auto road M-7 Volga – “Urazbakhtino” 7.7 km long is finished.

10/31/2013

Menzelinsky Branch

Side drainage 1070 meters long was constructed on site “Aktanysh – Poisevo” on km 39+550 – 40+080 (3rd stage) in Aktanyshsky district of the Republic of Tatarstan”.

10/30/2013

Nizhnekamsky Branch

Reconstruction of the road network in settlement Yelantovo is finished.

10/26/2013

Menzelinsky Branch

Auto road “Almetyevsk-Musliumovo – Igenche” in Musliumovsky district of the Republic of Tatarstan (2.2 km long) was put into service.

10/22/2013

Menzelinsky Branch

Site “M-7” – Volga – Stary Irkenyash – Tatarskaya Mushuga”, part down to Kzyl Tiubyak. The roadsides were stabilized with lime, and construction of the auto road is going on here.

10/22/2013

Menzelinsky Branch

Site “M-7” – Volga – Stary Irkenyash – Tatarskaya Mushuga”, part from Kzyl Tiubyak down to Yelgabash. The roadsides are being stabilized with lime and auto road is being here.

10/18/2013

Menzelinsky Branch

Warning posts and road signs are being mounted on site “Construction of the auto road “Almetiyevsk-Musliumovo” – Igenche” in Musliumovsky district of the Republic of Tatarstan.

10/17/2013

Aksubaevsky Branch

Auto road “Chistopol-Aksubayevo-Nurlat-Chuvashskoye Yenoruskino-Ilyashkino” in Aksubayevsky district of the Republic of Tatarstan was successfully put into operation.

10/17/2013

Aksubaevsky Branch

Auto road “Chistopol-Aksubayevo-Nurlat-Chuvashskoye Yenoruskino” in Aksubayevsky district of the Republic of Tatarstan was successfully commissioned.

10/11/2013

Mamadyshsky Branch

Auto road “Kemesh-Kul-Algayevo” is being prepared for commissioning.

10/11/2013

Nizhnekamsky Branch

The works are finished on site M-7 “Volga”-Ureyevo-Chelny-Kutlu Bukash-Berdibyakovo in Rybno-Slobodsky district of the Republic of Tatarstan.

10/09/2013

Aksubaevsky Branch

Roadside ditches are being stabilized with macadam on auto road “Chistopol-Aksubayevo-Nurlat”-Chuvashskoye Yenoruskino in Aksubayevsky district of the Republic of Tatarstan.

10/07/2013

Reconstruction of the auto road “Menzelinsk-Biyurgan” in Tukayevsky district of the Republic of Tatarstan. Here, metal guard rails are being installed.

10/05/2013

Menzelinsky Branch

As a part of preparation of auto roads and their engineering structures for autumn and winter period, the grass is being mowed on the roadsides and slopes, macadam and gravel roads are being shaped, and grass and bush is being removed from gutters of pipes.

10/03/2013

Apastovsky Branch

Reconstruction of the auto road “Bolshiye Memi – Zabornaya Polyana” in Verkhneuslonsky district of the Republic of Tatarstan is finished.

10/03/2013

Apastovsky Branch

Auto road “Bypass of settlement Bolshiye Kaibitsy ” km 0+000 – km 3+610 in Kaibitsky district of the Republic of Tatarstan is put into operation.

10/03/2013

Apastovsky Branch

Construction of macadam roadbed on auto road “Ulanovo-Karatun - Bolshiye Kaibitsy ” km 0+150 – km 8+360 in Apastovsky district of the Republic of Tatarstan.

10/03/2013

Аrsky Branch

On site “Reconstruction the auto road M-7 “Volga” – Shadki – Saush – Sharmashi, part Saush-Shadki in Tiuliyahinsky district of the Republic of Tatarstan” (on part Route #2) asphalt bedding course is being laid.

10/02/2013

Apastovsky Branch

Auto road Sobolevskoye-Chulpanikha in Verkhneuslonsky district of the Republic of Tatarstan is complete and put into operation.

10/02/2013

Asphalt-concrete coating was laid on site “Reconstruction the auto road “Ulanovo-Karatun” – Kaby Kopri, part Utiyamishevo - Kaby Kopri in Apastovsky district of the Republic of Tatarstan.

10/02/2013

Menzelinsky Branch

Binder is being laid over base course stabilized with cement on site “Verkhniy Tabyn - Togashevo”.

10/02/2013

Sabinsky Branch

Repair works are finished on sites:

  1. Reconstruction of the auto road “Timershik – Bolshoy Shinar”, km 4+200 – km 11+200 in Sabinsky district of the Republic of Tatarstan;
  2. Reconstruction of the auto road “Timershik – Bolshoy Shinar” - Uyut, km 1+100 – km 2+500 in Sabinsky district of the Republic of Tatarstan;
  3. Construction of the auto road “Kukmor - Shemordan” – Nyriya – Ishtugan” – Baldy Knya in Kukmorsky district of the Republic of Tatarstan.

10/02/2013

Apastovsky Branch

As a part of preparation for road maintenance during winter period, pothole repair is being made on the roads and machinery is being prepared for winter-time operation.

10/01/2013

Apastovsky Branch

On site “Drive to Tetiushi quay in Tetuishsky district of the Republic of Tatarstan” retaining wall on screw pile foundation is being constructed by subcontractor “SPC “Mosty” Ltd.