June - July 2011

June - July 2011

07/27/2011

Nizhnekamsky Branch

Placing of asphalt-concrete coating performed at the motor road Chistopol’ – Nizhnekamsk, section Detour of township Kamskie Polyany.

07/25/2011

Repair work is finishing at the motor road Khornovar Shigali – Novye Shigali in Drozhzhanovsky district of RТ.

07/25/2011

Nizhnekamsky Branch

Work for stabilization of soil with lime performed at the motor road Zainsk - Sukharevo.

07/25/2011

Nizhnekamsky Branch

Repair work performed at the section km 80+620 - km 86+940 of motor road Chistopol’ - Nizhnekamsk.

07/21/2011

Mamadyshsky Branch

Ready to be put into service is motor road with coating of transitional type Highway М-7 "Volga" – Baskan in Mamadyshsky district of RТ, length 2 km.

07/21/2011

Аrsky Branch

Repair work performed at the motor road Kazan – Malmyzh, section km 57+350 - km 61+ 832 in Arsky district of RТ.

07/17/2011

Аrsky Branch

Placing of asphalt-concrete at the approach to village Ishnarat in Arsky district of RT.

07/16/2011

Apastovsky Branch

Making of foundation using technique of cold recycling with cement strengthening (mixing at the site) at the approach to village Malye Kokuzy in Apastovsky district of RТ.

07/16/2011

Sabinsky Branch

Repair work performed at the motor road Kazan – Shemordan – Yulbat – Yusup Alan.

07/05/2011

Menzelinsky Branch

Work is being finished for making of substrate layer and broken-rock foundation at the motor road highway М-7 "Volga" – Staraya Aleksandrovka – Bikbulovo.

07/02/2011

Apastovsky Branch

Making of substrate layer and broken-rock foundation performed at the motor road Kazan – Ulianovsk – Kamskoe Ust’e – Varvarino. Work for making the leveling layer of black broken rock is performed in settlement Ten’ki in Kamsko-Ust’ensky district of RТ.

07/02/2011

Mamadyshsky Branch

Making of roadbed and constructive layers of pavement at the motor road Ishkeevo – Nizhniy Takanysh performed with the use of systems for 3D leveling at the bulldozer and motor grader CATERPILLAR.

06/29/2011

Suburban Branch

Final grading of foundation, made with regeneration technique, performed at the repair site at motor road Laishevo – Kurmanakovo, section km 0+000 - km 1+450 in Laishevsky district of RТ.

06/29/2011

Apastovsky Branch

Stabilization of excessively humidified soil with lime at the motor road Bol’shie Kaibitzy – Kamylovo – Maloe Podberez’e, section km 4+700 - km 6+700.

06/22/2011

Menzelinsky Branch

Work for making roadbed performed at the sites: road Menzelinsk – Kur’ya; highway М-7 "Volga" to road Staryi Irkenyash – Tatarskaya Mushuga.

06/20/2011

Mamadyshsky Branch

Finished is the repair work with making the asphalt-concrete coating at the motor roads: Kazan – Shemordan – Pukal’ (1.355 km) and Timershik – Bol’shoi Shinar (1.377 km).

06/16/2011

Reconstruction of motor road Saklov Bash – Suly – Saklovo.